Taw Wharf - Site Update

We are delighted to announce that works for Taw Wharf, our new housing development at Anchorwood Bank, are progressing quickly.

Works to the first ten houses and waterside apartments are continuing apace.

Block D

The concrete infill for the floor planks on level one and two are now complete.  The superstructure is due to commence in early June with the construction of the timber frames due in early August.

Plots 91 -100

The floor planks for plots 91-95 are now in place.  Works to install the floor planks for plots 95-100 are due to commence in early June, with the superstructure build currently on going.

Plots 69-80

The preparation of the piling mat has commenced with the pilling due to start in mid June. Construction of the road will also begin at this time.