Taw Wharf - Site Update

We’re pleased to say that since our last update we have handed over 5 homes on the western side of site to new families moving into Taw Wharf.

As we now focus on the eastern side of site we can see roof construction is underway on the first plots on the riverfront and roof covering to commence in just a few days.

On the south facing garden plots superstructure and masonry has reached the second and floor levels on many plots and work continues along the terrace.

The same is true of Block D2, which the superstructure reaching the 3rd floor and the timber frame construction beginning.

Further into the site substructure block work is now complete with ground floor block and beam now underway.