Regeneration Blog

Our blog follows the progress of Development & Regeneration Schemes being undertaken by North Devon Homes within the North Devon area.  Currently these schemes include regeneration of Lamaton Park in South Molton, new build homes at Gorwell, redevelopment of various garages sites and the regeneration of Anchorwood Bank.

18Sep

A big NDH weclome to our new shared owners!

We are delighted to announce that we have completed on a significant amount of shared ownership properties this financial year. Developments which include Tarka Way in Braunton, Osborne Gardens and Highgrove in Barnstaple and our newest development at Taw Wharf.

We would like to take this opportunity to welcome all our new shared owners and hope they are settling in well to their new homes!

As next week is Shared Ownership Week, we would like to remind people that we still…

Read more...
01May

Lamaton Park - Site Update

We are delighted to announce that works on our development at Lamaton Park in South Molton is advancing quickly.

The exterior is nearing completion with the interior decorations quickly progressing.

 

Read more...
04Apr

Osborne Gardens - New Properties Complete

We are pleased to announce that on Monday 25th March, North Devon Homes received handover of 12 new properties at Osborne Gardens in Barnstaple.

This development provides a range of rented and shared ownership properties

We hope that all our new customers are settling well into their new homes.

Read more...
04Apr

Lamaton Park - Site Update

We are delighted to announce that works at Lamaton Park in South Molton is progressing quickly.

Internal and external decorations have now commenced and this site is quickly becoming a significant feature within the community.

 

Read more...
14Mar

Taw Wharf - Site Update

We are delighted to announce that although the weather has not been on our side recently, progress at Taw Wharf  is advancing rapidly.

The 3 and 4 bedroom townhouses are perfect for open plan living with great spaces to relax and unwind with beautiful views of the River Taw.

The duplex penthouses are fast becoming a significant feature within the landscape and feature two spectacular rooftop terraces.

The shared ownership…

Read more...
08Feb

Taw Wharf - Site Update

We are delighted to see the Taw Wharf development fast becoming a significant feature within the heart of Barnstaple as works on site are progressing quickly.

Following the recent success of the Taw Wharf launch event, attendees where given the opportunity to reserve plots for purchase.  If you were unable to make the launch event please contact either Webbers Estate Agents or visit the…

Read more...
14Jan

Highgrove, Barnstaple - New Properties Complete

We are pleased to announce that North Devon Homes have now received handover of the remaining affordable homes and 3 shared ownership properties at Highgrove, Barnstaple from Pearce Construction.

We hope all our new customers are settling well into their new homes.

Read more...
14Jan

Jordan Close, Barnstaple - New Properties Complete

We are delighted to announce that North Devon Homes received handover of 2 new affordable bungalows and one new affordable home from Pearce Construction on Monday 7th January.

We hope all our new customers are settling well into their new homes.

Read more...
11Jan

Osborne Gardens, Site Update

Osborne Gardens is quickly starting to take shape with the external decorations complete and the internal decorations on going to plots 18, 19 and 20.

The 1st Fix trades have commenced on plots 1-5 with the plaster boarding in progress for plots 6-8.

This site will provide a range of affordable homes as well as two, 3 bedroom shared ownership houses available in March 2019. If you are interested in a shared ownership property please register on Help to Buy South West.

Read more...
11Jan

Lamaton Park, Site Update

We are pleased to announce that works at Lamaton Park in South Molton are progressing quickly.

The external block work is on going to Block A and the 1st fix carpentry plumbing and electrics are now complete.

The windows, doors and roof covering are all complete to Block C.

This site is due for completion in August 2019.

Read more...