Taw Wharf, Barnstaple

Works are continuing apace at Taw WharfNorth Devon’s highly anticipated new housing development located at Anchorwood Bank. The name references the local history and riverside location of the site, and also reflects our aspirations for the development which will help create a new neighbourhood set in the heart of Barnstaple. The housing development forms part of the wider regeneration of the whole site which will also include an area for shopping, eating and relaxing.

The steel frames for the first waterside apartment blocks are being installed and the first ten houses are starting to take shape.

Block D

The third floor is complete and all the steel work is now in place.  The floor planks are due to be in place within the next 2 weeks, followed by concrete infill to the top floor. Works to construct the superstructure are due to commence on the 11th June.

 

Plots 91-100

The superstructure for plots 91-100 will reach first floor height by the end of May.

Plots 69-80

The piling mats are currently being laid.  Once this is complete, the piling is due to commence on 11th June.