Taw Wharf, Site Update

We are delighted to announce that progress at our development on Taw Wharf is progressing apace.

The timber frames and roof coverings to plots 14-18 are now complete. The superstructure to plots 19-20 are nearing first floor height.

The steel frame and concrete planks to block C are complete and the lift has been tanked with block work to ground level.

The superstructure is being built to the 4th floor of block D.